N. Pima Rd. & E. Stagecoach Pass
Scottsdale, AZ
-

BACKGROUND
As part of our on-call contract with the City of Scottsdale, MTJ Roundabout Engineering was tasked with development of a concept roundabout design at this high-speed rural intersection. The concept design is in support of feasibility determination and programming purposes.
-
SUMMARY
The resulting concept horizontal geometric design was predicated on application of traffic/highway engineering and modern roundabout design principles and criteria working together to optimize safety for this high-speed rural application.
Key Project Outcomes:
Address driver expectancy for high speed context
Minimize adverse impacts
Accommodate large trucks/freight
Transit and school buses
Highlights
135′ single-lane design
Provisions for residential access near intersection
ROW constraints
Minimized adverse impacts
Large trucks/freight accommodations
Addressed driver expectancy for high-speed context